Taping of the drywall on the third floor is being done
this week, with painting starting on January 5th.
Drywall
installation on the second floor should be finished by Saturday.
(12/17/03)
Siding installation on the west side of the building has
begun. (12/17/03)
Framing for the gas fireplace in the library on the first
floor. (12/10/03)
View from the west of the building. Windows
installed.
(12/3/03).

Aerial photo courtesy of Walsh Construction (11/14/03)
Siding will begin on Nov 20th, installation of windows
continues. (11/19/03)
View from the east in to the courtyard. (11/12/03)
View of courtyard. Roof shingles are almost
complete, the first floor windows have been installed,
and a
humidifier/heater is at work drying the building out. (11/12/03)
(11/5/03)
View towards the west in the courtyard; the low overhang
covers the entrances to both the
library and community room.
(11/5/03)
View towards Angle Lake from the southwest stairwell.
(11/5/03)

Aerial photo courtesy of Walsh Construction (10/31/03).
View of Angle Lake Senior Housing from the east.
(10/29/03)

Aerial photo courtesy of Walsh Construction of Angle
Lake Senior Housing, taken 10/14/03.
The roof is being installed on the north wing. The shingles should start
going on the first week of November. (10/15/03)
View of the north wing of the building. (10/15/03)
Rough-in for plumbing, electrical, phones and cable
has started. (10/1/03)
Return to Angle Lake Senior Housing most recent
photos.
Return to LATCH homepage.