Landscaping of courtyard has started and painting is
almost complete. (3/10/04)

View of the courtyard. (3/10/04)
Photo of the community room kitchen. (3/3/04)
Painting of the main entrance is underway and light
fixtures have been installed. (2/25/04)
Painting continues as weather allows. Work on the
trellis' continues. (2/25/04)
Handrails have been installed on the third floor.
Work on units on the 3rd floor will be complete by 2/20. (2/18/04)
|
|
|
Painting on the south and north sides is almost complete,
and will continue as weather permits. Landscaping on the south and
north sides has started. (2/18/04).
Painting on the north side of the building continues, and
has begun on the south side. (2/11/04)
Example of the views units will have of Mt. Rainier and
Angle Lake. (2/11/04)
Carpeting has been installed on the third floor and all
trim work complete. (2/11/04)

Aerial photo of construction. Courtesy of Walsh
Construction Company. (2/2/04)
|
|
|
We went out to the site today and approved the paint mock-up. Painting should begin Monday with a window of good weather. (2/6/04)
Carpet installation on the third floor has started.
(2/6/04)
The library on the first floor. (2/4/04)
Trim work on the third floor is finished and carpet
installation has begun. (2/4/04)
|
|
|
|
|
Unit entries. |
View of kitchen from living room. (2/4/04)
Siding on the south side is complete, and continuing on
the courtyard. The concrete walkways have been poured.
(1/5/04)
Installation of landscaping has begun on the periphery. (1/5/04)
|
|
|
Kitchen cabinets, lights and vinyl flooring have been installed on the third floor. Doors have been installed on third floor and trim work is almost complete. (1/5/04)
View of the community room on the first floor.
Painting will begin next week. (1/5/04)

Aerial photo of construction site taken January 5th,
courtesy of Walsh Construction Company. (1/5/04)
Siders have completed the south side of the building and
begun work in the interior courtyard. Concrete patios at unit
entries and common room in courtyard, courtyard patios, and sidewalks
have all been poured. Landscaping on the periphery has begun.
(1/21/04)
Cabinet installation has begun on the third floor and
trim packages are onsite. Second floor interior is painted, and
first floor taping is almost complete. (1/21/04)
Sidewalks are being poured, and siding on the south and
east sides continue. (1/14/04)
Lighting on third floor is going in, and gypcrete has
been poured. Trim work on the third floor will start next week.
(1/14/04).
Siding continues on the west and south sides of the
building (main entrance on west shown here). (12/31/03).
Siding on the north side of the building is complete.
We're waiting for a warmer drier day to do a paint mock-up.
(12/31/03).
On the third floor, wall texture has been applied and
units
are to be painted this week. (12/31/03).