The trellis features are almost complete, security
cameras installed, and lighting done. (4/22/04)
Landscaping is flowering in the courtyard, patio fences
have been installed and vines planted. (4/22/04)
Individual unit patios with fences, and the courtyard
patio. (4/22/04)
Courtyard landscaping is complete. Entries to
ground floor units and patios. (3/31/04)
The entry lobby is complete and looks great- finish
carpentry turned out really nicely. This view is looking from the
front door to the elevator lobby and manager's unit. (3/31/04)
Work on the columns supporting the courtyard overhang
should be complete by next week. We'll start fishing around soon
for a donation of a gas grill for the patio. (3/31/04)
Work on the trellis feature at the front entrance is
almost complete. Site signs are almost completely installed and
the overlay and striping is complete in the parking lot. Gutter
installation started today. (3/31/04)
Trellis seen from the front entrance going towards South
188th Street. (3/31/04)
Work in the community room and the library on the first
floor will be the last thing completed. (3/31/04)
Work on the trellis' at the east side of the building is
ongoing. (3/31/04)
Third and second floor units and common areas are almost
complete, and most landscaping is installed and blooming.
(3/24/04)
Lobby finishes are being completed and parking lot
overlay is done. (3/24/04)

Aerial photo courtesy of Walsh Construction. (3/1/04)